A £200m data-centre proposal for Microsoft’s former Thames Valley headquarters site could require up to 110MW of electricity, far more than the 1.8MW of National Grid capacity currently available there. The application puts energy supply, interim gas generation and a possible future heat network at the heart of a planning decision expected by March.
Watch Desk analysis
What happened
Mapeley has submitted plans to Wokingham Borough Council to demolish three office buildings at Thames Valley Park in Earley and build a data centre. The BBC reports that the main buildings could reach 30.5 metres, or about ten storeys. The proposal includes on-site power generation equipment, backup generators and office space.
The developers propose using natural gas while waiting for the local electricity network to be upgraded. They also say waste heat could eventually supply a district heating network serving places including the Royal Berkshire Hospital, the University of Reading and local schools. The application says the facility would create up to 65 jobs once operational.
Why it matters
The power gap is the sharpest practical question in the proposal: 110MW of potential demand against 1.8MW currently available from the grid. The plans therefore depend, at least initially, on on-site generation, while the promised heat network remains a possible future benefit rather than a present one.
Residents have raised concerns about noise, heat, emissions, wildlife and the site’s proximity to Thames Valley Park Nature Reserve. The proposal also claims a biodiversity net gain of more than 22%. Those claims, and the trade-offs between local impacts and digital infrastructure, are now part of the planning discussion.
Our read
This is a computing-infrastructure story with a very physical footprint: the cloud still needs land, power and neighbours. The old Microsoft address may make a neat headline, but Mapeley submitted the application; this is not a Microsoft data-centre project. The key test is whether the council can weigh the stated local benefits against the energy and environmental questions before it.
What to watch
- Wokingham Borough Council’s decision, expected by March.
- How the proposed gas generation and grid upgrade are addressed in the planning process.
- Whether the district-heating proposal gains firm details, including how it would be delivered.
Discussion spark: Should councils approve data centres when developers promise future heat and jobs, or require firm power and environmental guarantees before construction?