Meta’s review of its 2030 net-zero target comes with a wider environmental bill than carbon alone: its latest figures show water use rising in stressed locations and through the electricity it buys. The company has not announced a replacement target, but the numbers sharpen the question of what its expanding AI infrastructure will cost.
Meta AI Watch analysis
What happened
TechRadar reports that Meta’s sustainability figures put direct water use at 790 million gallons, including 246 million in water-stressed locations. Direct use fell 4% overall, while use in stressed locations rose 24%. Water consumption associated with purchased electricity climbed 37%, reaching 26.1 billion gallons, the report says.
The same report says Meta’s electricity use rose 35% to 24.8 terawatt-hours in 2025. The company reported more than 30 gigawatts of contracted clean-energy capacity, with almost 12 gigawatts operational, and is considering natural-gas generation where utilities cannot supply power quickly enough. Meta’s executives say the company is reassessing its 2030 goal and interim milestones; no new timetable has been announced.
Why it matters
A data centre’s footprint is not just the electricity meter or the carbon total. Water use can land hardest in places already under pressure, while power generation adds another indirect draw. Meta’s figures make those trade-offs more visible as it expands computing for AI.
These are figures and plans reported from Meta’s disclosures, not a new commitment to cut water use or abandon the net-zero goal. The missing piece is what the company will change, and when.
Our read
The water numbers deserve a place in the AI infrastructure debate, not a footnote after the gigawatts. Meta has put useful figures on the table; now it needs targets that show whether growth in computing can be matched by progress on local water and emissions.
What to watch
- Whether Meta changes its 2030 target or interim milestones, and what replaces them.
- Whether it publishes clearer targets for water use in stressed locations.
- How quickly contracted clean-energy capacity becomes operational, and where gas generation is used.