Norway’s regional state administrator has revoked approval for a planned £2bn AI data centre at Tonstad, saying the project was waved through without a full planning process and impact assessments, The Telegraph reports. The decision puts the project’s next steps back in question, with endangered eagle owls among the concerns raised by objectors.
Watch Desk analysis
What happened
The project, planned by British developer GreenScale, had been backed by local politicians in Sirdal municipality. The administrator’s decision followed complaints that proper planning rules had not been followed and that potential effects on wildlife, noise, power use and heat had not been properly assessed. The local authority must now decide whether to seek fresh approval, a process that could delay work for months.
The Telegraph reports that GreenScale said it remained committed to the project and would follow the required processes. Local politicians argue that the site was earmarked for industrial development as early as 2013 and say a bird survey was carried out. The report says an independent three-week survey submitted in 2025 did not detect eagle owl activity. Those points do not settle the planning question: the administrator’s objection was that the approval process and assessments were inadequate.
Why it matters
This is a concrete test of what it takes to build AI infrastructure, not just a debate about how much computing power is wanted. A project can have political backing, a proposed industrial site and a claimed economic case, yet still face delay if planning and environmental scrutiny are found wanting. Power and land are part of the AI build-out; so are the rules governing where facilities go.
The dispute also has a useful distinction at its centre. GreenScale and local politicians say the project can proceed responsibly, while objectors and the administrator raise questions about whether the process properly assessed the risks. Those are competing positions, not a verdict on the project’s eventual impact.
Our read
A £2bn price tag does not buy a shortcut through planning, and that is probably healthy. The next meaningful development is whether the authority pursues fresh approval and what evidence a new assessment provides, particularly on wildlife and the site’s broader effects.
What to watch
- Whether the local authority seeks fresh approval and how long that process takes.
- What any new impact assessments say about eagle owls and other environmental concerns.
- Whether GreenScale changes its plans or provides further evidence about the project’s effects.
- How the decision affects the wider push to build data centres for AI.
Discussion spark: When a major AI data-centre project promises investment but faces unresolved environmental and planning concerns, should authorities prioritise speed or require a fresh assessment before it proceeds?
Sources and evidence
- Endangered owls delay plans for £2bn data centre – The Telegraph (23 November 2026, 08:00 UTC)
Watch Desk is operated by WittyWires as an independent cross-cutting AI news tracker. It does not speak for the organisations or people it covers.