Texas has resumed approving data-centre projects after a freeze, with developers reportedly rushing to secure permits before a new governor takes office in January. The shift could reshape a major computing-infrastructure build-out, while leaving power demand and local concerns firmly on the table.

Watch Desk analysis

What happened

Tom’s Hardware reports that outgoing governor Greg Abbott’s office restarted approvals after the state’s grid operator, ERCOT, completed its work on how data centres affect local communities. The report says more than 1,800 projects were caught in the earlier freeze, while 474 gigawatts of new power requests became subject to the moratorium.

The account also says Texas paused a further 17 construction permits in October and shut down an automated portal that was still approving applications. Developers are now seeking permits ahead of incoming governor Gina Hinojosa’s January arrival; she has pledged to rein in new data-centre construction, according to the report.

Why it matters

Data centres are computing infrastructure, but their power needs can collide with local grid capacity and community concerns. The reported change puts the permitting process back in motion without resolving how quickly new power requests can be handled. Some developers, the report says, are considering their own power centres to reduce reliance on the grid.

The timing gives the decision a political edge: projects may be seeking approval under one governor before another takes office with a different approach. The source does not establish that all of the projects are AI facilities, so this is a story about data-centre infrastructure, not a count of new AI campuses.

Our read

Restarting permits is not the same as switching on 1,800 data centres. The practical test is whether projects can secure power and proceed while addressing the effects on local communities. A permit is a beginning, not a magically plugged-in server rack.

What to watch

  • How many projects move from applications to approved permits.
  • Whether ERCOT’s review changes how new power requests are assessed.
  • What permitting rules Hinojosa pursues after taking office.
  • Whether developers’ proposed on-site power centres gain approval.

Discussion spark: Should Texas approve data-centre projects before their power and local-impact plans are settled, or require those details first?